Array
(
[0] => Array
(
[id] => 2
[name] => 首页
[category_id] => 221
[url] =>
[active] => 1
[position] => 1
[blank] =>
[is_out] =>
)
[1] => Array
(
[id] => 4
[name] => 氿上商城
[category_id] => 221
[url] => goods
[active] => 1
[position] => 2
[blank] =>
[is_out] =>
)
[2] => Array
(
[id] => 1
[name] => 学习园地
[category_id] => 221
[url] => news
[active] => 1
[position] => 5
[blank] =>
[is_out] =>
)
[3] => Array
(
[id] => 16
[name] => 氿上知道
[category_id] => 221
[url] => question
[active] => 1
[position] => 4
[blank] =>
[is_out] =>
)
[4] => Array
(
[id] => 5
[name] => 供求信息
[category_id] => 221
[url] => trade
[active] => 1
[position] => 3
[blank] =>
[is_out] =>
)
[5] => Array
(
[id] => 3
[name] => 软件下载
[category_id] => 221
[url] => jsyjj/list/409
[active] => 1
[position] => 6
[blank] =>
[is_out] =>
)
[6] => Array
(
[id] => 46
[name] => 氿上云管理
[category_id] => 221
[url] => yun/index
[active] => 1
[position] => 7
[blank] =>
[is_out] =>
)
[7] => Array
(
[id] => 22
[name] => 氿上花园
[category_id] => 221
[url] => garden
[active] => 1
[position] => 999
[blank] =>
[is_out] =>
)
)
各位前辈,抹灰的接口位置有好的施工方法吗? - 工程施工 - 项目管理 - 氿上知道
返回顶部
满意答案
抹灰前灰饼或冲筋先对点位密一点,如果确实需要留接口,第一次抹灰比预留接口位多抹10CM左右,磨平压实后靠尺完全刮平达到平整度要求后,,马上用靠尺沿预留边压边用铁板切割缝口,将多抹上去的部分清除,第二次抹上去后接口缝上面就相当于一条整的冲筋带了,接口位置也很平整。
但主要是要加强工人的责任感,第一次抹灰一定要平整。
LilyZ
回答于:2013-09-13